Which part of the conference actually decides the date?

Event plans feel uniformly urgent, and that is exactly why they slip: attention gets spread evenly across tasks that matter very differently. One run tells you where the pressure genuinely is.

Words on this sheet

  • Predecessors: The tasks that have to finish before this one can start. Put their IDs here, separated by commas, and leave it blank when nothing has to come first.
  • Venue: The place an event is held. A venue line is what hiring it costs, usually a fixed amount whatever the turnout.

Marketing Starter Critical Path Pro engine

After you install, this is the model to open.

Conference Plan: What Sets the Date?

  1. In your spreadsheet, click the Sortia icon in the strip of icons down the right-hand edge. No strip? Click the arrow at the bottom-right to open it. You can also use Extensions, then Sortia, then Open Sortia.
  2. Click Start from a template and put that name in the search box.
  3. Pick the card with that name and click Load this template. It arrives on a new tab with real numbers already in it.

This one runs on a Pro engine, and every free install includes five full-quality runs on your own numbers, shared across all five Pro engines rather than five for each. After that, Pro is $199/year.

The answer

The path and the slack:

Ready on
Day 32
Sets the date
Speakers 14 days
Registration slack
20 days
Rehearsal slack
3 days

The conference is ready on day 32, driven by venue, speakers, program and materials. Registration carries 20 days of slack, which reframes the whole plan: every week a speaker takes to confirm is a week on the finish date, while registration can open late at no cost. Chase speakers, not the registration page.

The model

Six tasks. Registration and the speaker track both follow the venue decision, then converge on the rehearsal.

Lock date and venue6 days
Confirm speakers14 days, after venue
Open registration4 days, after venue
Build the program7 days, after speakers
Print and ship materials5 days
Run the rehearsal2 days

Once it is in your sheet

  1. The model arrives with real numbers in it and runs as it stands, so you can press the button first and understand it second.
  2. Change the numbers to yours. The sheet marks which cells are inputs and which hold formulas, and most labels carry a note explaining the row.
  3. Press the run button at the bottom of the panel. It is labeled for the tool you are in, and the result lands on its own tab, with a written reading of it beside the figures.

Never used Google Sheets? Start here goes the whole way, in seven steps, and assumes nothing.